"/>
Spotlight: Seven years on, Fukushima nuclear cleanup still long way to go
Source: Xinhua   2018-03-11 20:29:28

TOKYO, March 11 (Xinhua) -- Seven years after one of the worst nuclear disasters in history, Japan is still struggling with the aftermaths, not only the tough tasks of reconstruction, but also nuclear cleanup work that is expected to take generations, with hefty costs and unsolved technical problems.

The massive earthquake and the ensuing tsunami on March 11, 2011 severely damaged three reactors at Daiichi facility in Fukushima, which suffered core meltdowns after their key cooling systems were knocked out and backup power supplies rendered useless.

Tokyo Electric Power Company Holdings Inc. (TEPCO), operator of the crippled Fukushima Daiichi nuclear plant, had since successfully decommissioned the No. 5 and 6 reactors at the plant, and more than 1,500 fuel rods in the No. 4 reactor had been taken out and safely stored by the end of 2014.

But the problem lies with removing the melted nuclear fuel and debris from the No.1 to 3 reactors, which, according to experts, poses the biggest challenge to the decommission work.

The Japanese government and TEPCO have made plans to start fuel removal from the three reactors in 2021, but experts have expressed doubts regarding whether the plan could be carried out as scheduled.

Toyoshi Fuketa, Nuclear Regulation Authority Chairman, told a press conference recently that the removal work has not yet reached a point where "exit is in sight."

One of the difficulties lies in the extremely high radiation levels inside the reactors.

TEPCO said last month that levels of radiation detected inside the No. 2 reactor in a January probe were as high as 7-42 sieverts per hour, still enough to kill a person for just a short period of exposure.

The operator of the crippled plant, having established the path of conducting the cleanup work through remote mechanic systems, is still struggling with finding more viable technical solutions to the process.

The whole process also comes with a hefty price tag. According to Japan's Ministry of Economy, Trade and Industry, the cost of the decontamination work and treatment of polluted water, is expected to surge to 8 trillion yen (75 billion U.S. dollars) in total.

The number was much higher according to the calculation of a civil group Atomic Energy Citizens' Committee, reaching roughly 30 trillion yen (281 billion U.S. dollars).

Other thorny problems include decontaminating the soil and treating the contaminated water.

To keep the No.1 to 3 reactors cooled, TEPCO has to inject a large amount of fresh water into the reactors constantly. The water becomes radioactive in the process and is then stored in the basement of the reactor buildings. TEPCO's "decontamination" facilities can remove radioactive cesium and strontium from the water but not tritium.

TEPCO released a limited amount of radioactive water into the Pacific Ocean after getting approval from the local fishery association in September 2015. But there is not enough scientific research to determine that dumping contaminated water into the ocean is safe.

Some much-vaunted measures turned out not as efficient as they were originally planned while costing a huge sum of the money.

A government-commissioned group of experts concluded recently that a costly underground ice wall is only partially effective in reducing the ever-growing amount of contaminated water at the nuclear plant.

The wall cost 34.5 billion yen (323 million U.S. dollars) to build and is expected to cost more than 1 billion yen (9.4 million U.S. dollars) annually in operating and maintenance.

Most of the hefty expenses would have to be borne by taxpayers, as TEPCO, which was bailed out by the government, has been grappling with difficult financial situations when coping with the lengthy task of decommissioning the plant and carrying out cleanup work which is likely to take decades.

The operator of the Fukushima Daiichi nuclear plant has also been hit with a number of lawsuits for alleged negligence or improper design, construction and maintenance of the nuclear facilities.

"The multiple disasters that struck Fukushima seven years ago are not something that just belongs to the past, but are still affecting us," said Fukushima Governor Masao Uchibori.

Editor: Chengcheng
Related News
Xinhuanet

Spotlight: Seven years on, Fukushima nuclear cleanup still long way to go

Source: Xinhua 2018-03-11 20:29:28
[Editor: huaxia]

TOKYO, March 11 (Xinhua) -- Seven years after one of the worst nuclear disasters in history, Japan is still struggling with the aftermaths, not only the tough tasks of reconstruction, but also nuclear cleanup work that is expected to take generations, with hefty costs and unsolved technical problems.

The massive earthquake and the ensuing tsunami on March 11, 2011 severely damaged three reactors at Daiichi facility in Fukushima, which suffered core meltdowns after their key cooling systems were knocked out and backup power supplies rendered useless.

Tokyo Electric Power Company Holdings Inc. (TEPCO), operator of the crippled Fukushima Daiichi nuclear plant, had since successfully decommissioned the No. 5 and 6 reactors at the plant, and more than 1,500 fuel rods in the No. 4 reactor had been taken out and safely stored by the end of 2014.

But the problem lies with removing the melted nuclear fuel and debris from the No.1 to 3 reactors, which, according to experts, poses the biggest challenge to the decommission work.

The Japanese government and TEPCO have made plans to start fuel removal from the three reactors in 2021, but experts have expressed doubts regarding whether the plan could be carried out as scheduled.

Toyoshi Fuketa, Nuclear Regulation Authority Chairman, told a press conference recently that the removal work has not yet reached a point where "exit is in sight."

One of the difficulties lies in the extremely high radiation levels inside the reactors.

TEPCO said last month that levels of radiation detected inside the No. 2 reactor in a January probe were as high as 7-42 sieverts per hour, still enough to kill a person for just a short period of exposure.

The operator of the crippled plant, having established the path of conducting the cleanup work through remote mechanic systems, is still struggling with finding more viable technical solutions to the process.

The whole process also comes with a hefty price tag. According to Japan's Ministry of Economy, Trade and Industry, the cost of the decontamination work and treatment of polluted water, is expected to surge to 8 trillion yen (75 billion U.S. dollars) in total.

The number was much higher according to the calculation of a civil group Atomic Energy Citizens' Committee, reaching roughly 30 trillion yen (281 billion U.S. dollars).

Other thorny problems include decontaminating the soil and treating the contaminated water.

To keep the No.1 to 3 reactors cooled, TEPCO has to inject a large amount of fresh water into the reactors constantly. The water becomes radioactive in the process and is then stored in the basement of the reactor buildings. TEPCO's "decontamination" facilities can remove radioactive cesium and strontium from the water but not tritium.

TEPCO released a limited amount of radioactive water into the Pacific Ocean after getting approval from the local fishery association in September 2015. But there is not enough scientific research to determine that dumping contaminated water into the ocean is safe.

Some much-vaunted measures turned out not as efficient as they were originally planned while costing a huge sum of the money.

A government-commissioned group of experts concluded recently that a costly underground ice wall is only partially effective in reducing the ever-growing amount of contaminated water at the nuclear plant.

The wall cost 34.5 billion yen (323 million U.S. dollars) to build and is expected to cost more than 1 billion yen (9.4 million U.S. dollars) annually in operating and maintenance.

Most of the hefty expenses would have to be borne by taxpayers, as TEPCO, which was bailed out by the government, has been grappling with difficult financial situations when coping with the lengthy task of decommissioning the plant and carrying out cleanup work which is likely to take decades.

The operator of the Fukushima Daiichi nuclear plant has also been hit with a number of lawsuits for alleged negligence or improper design, construction and maintenance of the nuclear facilities.

"The multiple disasters that struck Fukushima seven years ago are not something that just belongs to the past, but are still affecting us," said Fukushima Governor Masao Uchibori.

[Editor: huaxia]
010020070750000000000000011100001370320231
大发彩票 大发app 凤凰彩票app 乐发iv游戏平台 凤凰彩票大厅 乐发彩票 乐发彩票app下载 大发彩票 乐发v官网 乐发lll 乐发lv入口 乐发iv首页 乐发ll登录 凤凰彩票大厅 乐发官网 乐发ii下载入口 乐发ll 乐发v平台 乐发v官网 乐发lll 乐发lv入口 乐发iv首页 乐发ll登录 乐发lv 乐发lll安装 乐发lv 乐发登录入口 乐发iv游戏平台 凤凰彩票登录 网信彩票 彩神 彩神彩票官方网站 彩神彩票官网首页 彩神官方app下载安卓版 凤凰彩票登录 彩神v3 凤凰彩票app下载 彩神官方app下载安卓版 网信快三 一分快3 快三彩票购彩平台 凤凰彩票官方 快3官网 网信彩票 快3app 网信彩票平台 百姓彩票平台 网信平台官网 快3app下载 百姓彩票 每日彩票 快3app 百姓彩票 每日彩票 快3app 百姓彩票平台 幸运5分彩快3 快3彩票app下载 百姓彩票网站网址 大发10分PK10 快3下载 网信彩票平台 网信平台官网 快3彩票官网app 凤凰彩票官方 彩神彩票 大发10分PK10 彩神v3 大发彩票app下载 百姓彩票网站网址 彩神购彩平台 每日彩票 官方正规快三彩票平台 彩神彩票购彩平台 百姓彩票 凤凰彩票购彩平台 凤凰彩票app下载 彩神官方app下载安卓版 网信快三 一分快3 快三彩票购彩平台 凤凰彩票官方 彩神彩票 大发10分PK10 彩神v3 凤凰彩票登录 乐发lv 乐发∨Il 百姓彩票网站网址 乐发彩票 乐发彩票官方网站 乐发lll安装 百姓彩票网站网址 凤凰彩票app下载 大发10分PK10 乐发2 乐发app 凤凰彩票 大发彩票app 乐发登录入口 乐发ll登录 乐发v官网 乐发官网 大发彩票app下载 凤凰彩票购彩平台 彩神彩票 官方正规快三彩票平台 一分快3 百姓彩票网站网址 凤凰彩票app下载 大发10分PK10 乐发2 乐发app 凤凰彩票 大发彩票app 乐发登录入口 乐发ll登录 乐发v官网 乐发官网 大发彩票app下载 凤凰彩票购彩平台 彩神彩票 官方正规快三彩票平台 1分快三平台 百姓彩票平台 凤凰彩票登录 幸运5分彩快3 彩神 乐发彩票 乐发 大发彩票 乐发iv游戏平台 乐发lv 乐发lll 乐发ii下载入口 乐发彩票官方网站 凤凰彩票官方网站 凤凰快3 彩神彩票官网首页 1分快三平台 百姓彩票平台 凤凰彩票登录 幸运5分彩快3 彩神 乐发彩票 乐发 大发彩票 乐发iv游戏平台 乐发lv 凤凰彩票app 乐发app 网信彩票平台 网信彩票平台 乐发iv游戏平台 凤凰彩票app 乐发lv 乐发彩票app下载 凤凰彩票app 网信彩票平台 乐发彩票app下载 乐发lv 乐发app 大发彩票安卓下载 大发彩票安卓下载 大发彩票 乐发彩票app下载 网信彩票平台 乐发iv游戏平台 彩神彩票 乐发彩票中心 极速快3彩票平台 人人快三凤凰 大发彩票app 大发彩票大全 乐发彩票 彩神彩票官方网站 乐发app 酷天堂彩票平台 凤凰彩票app下载 凤凰彩票大厅 凤凰彩票app 极速快3彩票平台 凤凰彩票 凤凰快3 乐发ll官网 乐发彩票中心 正规快三送彩金平台 凤凰彩票官方 乐发ll 乐发 网信彩票 彩神彩票 彩神彩票官方网站 大发彩票app 网信彩票用户 百姓快三 百姓彩票平台 乐发lv 乐发彩票app下载 彩信平台 网信彩票 乐发彩票官方网站 乐发∨Il 人人快三凤凰 凤凰彩票 凤凰快3 乐发ll官网 乐发彩票中心 正规快三送彩金平台 凤凰彩票官方 乐发ll 乐发 网信彩票 彩神彩票 彩神彩票官方网站 人人快三凤凰 乐发彩票 彩神彩票 乐发iv游戏平台 乐发彩票 大发彩票中心 凤凰彩票登录 凤凰彩票app 彩神彩票 大发彩票 乐发ll 大发彩票app 凤凰快3 凤凰彩票 彩神彩票 乐发ll 凤凰彩票 乐发lll 凤凰彩票大厅 网信彩票 彩神彩票 乐发lv 快盈彩票 乐发彩票官方网站 盈彩网投资平台 大发官网 一分时时彩 乐发lv 快3平台 凤凰快3 乐发ll 全民彩票 乐发彩票官方网站 百姓彩票 乐发彩票 大发彩票 极速快3 乐发app 大发官网 乐发lll 快3平台 凤凰快3 乐发ll 全民彩票 乐发彩票官方网站 百姓彩票 乐发彩票 大发彩票 极速快3 乐发app 彩神iv 大发彩票app 大小单双平台 一分pk10 乐发lv 快盈彩票 乐发官网 快彩彩票 百姓彩票 凤凰彩票大厅 网信彩票 乐发彩票中心 网信快3 乐发 彩神xl 三分快3 大发彩票 大发官网 乐发lll 快3平台 凤凰快3 乐发ll 全民彩票 乐发彩票官方网站 百姓彩票 乐发彩票 乐发彩票官方网站 大发彩票 乐发 分分快3 彩神vl 55世纪 55世纪 凤凰快3 乐发彩票 乐发lv welcome凤凰彩票 乐发ll 1分快3 彩神 彩神ll 1分快3官网 1分快3的平台 welcome凤凰彩票 三分快3 彩神x 彩神vl 凤凰彩票 彩神xl 大发彩票 凤凰彩票大厅 乐发官网 乐发ll 乐发lll 乐发lv 大发彩票app 大发彩票 乐发 乐发彩票 乐发彩票中心 凤凰快3 乐发彩票 彩神xl 腾讯快3 大发彩票 彩神xl 大发彩票 乐发彩票 大发彩票app 快3平台 乐发 1分快3 乐发彩票 彩神x 凤凰快3 彩神xl 彩吧助手 大发彩票app 快3平台 大发排列3 彩神iv 彩神vl 乐发IV 彩神x 一分pk10 大发排列3 乐发lv 快3彩票 乐发app下载 三分快3 快三平台助手 乐发彩票ll 彩神iv 乐发lll下载 盈彩网投资平台 乐发Ⅲ 一分pk10 凤凰彩票 乐发Vll 大发官网 乐发ll 大发彩票 乐发1 凤凰快3 彩神vl 乐发lx 百姓彩票 乐发VI 彩神x 乐发IV 极速快3 乐发 凤凰快3 网信快3 乐发lv 快3彩票 乐发app下载 三分快3 快三平台助手 乐发彩票ll 彩神iv 乐发lll下载 盈彩网投资平台 乐发Ⅲ 凤凰彩票大厅 乐发lv 乐发lv 乐发lv 凤凰彩票 大发彩票 大发彩票 凤凰彩票 乐发lv 凤凰彩票 凤凰彩票 乐发lv 乐发ll 凤凰彩票app下载 凤凰彩票 凤凰彩票 乐发lv 乐发ll 凤凰彩票app下载 凤凰彩票 凤凰彩票 乐发lv 彩神x 乐发 乐发ll 极速快3 乐发lv 乐发彩票中心 快3彩票 凤凰彩票大厅 彩神x 凤凰彩票app 分分快3 网信彩票 网盟彩票 凤凰彩票 百姓彩票 乐发 快彩彩票 乐发彩票 快3平台 百姓彩票 大小单双平台 凤凰快3 彩神xl 一分pk10 乐发lv 三分快3 大发彩票 乐发彩票 快3平台 百姓彩票 大小单双平台 凤凰快3 彩神xl 一分pk10 乐发lv 三分快3 大发彩票 极速快3 乐发ll 网信彩票 乐发lv 全民彩票 凤凰彩票app下载 快盈彩票 大发彩票app 大发官网 凤凰彩票 彩神iv 大发彩票 网信快3 凤凰彩票 百姓彩票